RUSBURMASH, JSC implemented the project «Ready site» at the Vershinny deposit

The field in the Bauntovsky-Evenki District of the Republic of Buryatia is processed by Khiagda, JSC, which is also a subsidiary of the ARMZ Uranium Holding Co. Complex arrangement of production blocks as part of the «Ready site» project allows to reduce the construction costs of the entire mining complex due to efficient organization of work and optimization of technological process duration.
RUSBURMASH, JSC completed a comprehensive arrangement of the two production blocks of the field: engineering preparation of the construction site, construction and development of technological wells, well piping construction and installation work, arrangement of the power supply and instrumentation systems. The full complex of work was carried out by the separate structural unit Drilling Site No. 3. In total, 78 technological wells were constructed during the project implementation, more than 2500 rm of pipeline for transportation of technical solutions were installed, 18 thousand cubic meters of rock were poured out during the construction of roads.
The stated scope of work was completed by the specialists of the drilling site well ahead of the schedule, in 7 months instead of the planned 12. «We continue to improve existing competencies, develop technologies. Experience in the implementation of a similar project at the fields in the Kurgan region also helped us to shorten the implementation period,» said Yuri Mironov, Director General of RUSBURMASH, JSC.
«Previously, when arranging production blocks, we needed to work with several contractors, each of which carried out certain types of work. Now we have an optimal integrated solution, and a cheaper one,» noted Andrey Gladyshev, Director General of Khiagda, JSC. The obtained results allow RUSBURMASH, JSC to offer a complex arrangement of blocks to other mining enterprises.