Mine No. 6 construction continues on schedule

In April, it is scheduled to complete work on the 19-RESh shaft tipple pit and drive 771 piles to compact the soil. Earlier, the Krasnoyarsk Mining Company (contractor) employees drove 820 piles. A lifting machine and other necessary equipment will be installed in the shaft tipple. The contractor is implementing the CEP-project enabling to reduce significantly the time required for completion of the work. Work continues on the mine water treatment plant (MWTP) construction site, where the industry CEP-project is being implemented. The pipeline junction point construction has started on the temporary 20-P shaft drainage.
«This year, it is scheduled to launch the MWTP and to perfect the treatment technology. The Impulse water treatment plant buildings have already been built, pipelines laid, large-sized equipment has been installed. Our task is to prepare the mine site for dewatering in full scope,» says Ivan Kiselev, Director General of the PIMCU, PJSC.